Certificate replacement
Scheduled Maintenance Report for Optimizely Service
Completed
The scheduled maintenance has been completed.
Posted Jul 21, 2020 - 17:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 20, 2020 - 17:00 UTC
Scheduled
This maintenance will begin at 17:00 UTC on Monday July 20th
Posted Jul 14, 2020 - 21:32 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 14, 2020 - 21:27 UTC
Scheduled
The scheduled maintenance planned for 17:00 UTC was postponed by our 3rd party supplier at the last minute. We are currently requesting more information from them as to the reason for this postponement and to obtain a new date/time window for this maintenance to occur.
Posted Jul 14, 2020 - 21:27 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 14, 2020 - 17:00 UTC
Update
We will be undergoing scheduled maintenance during this time.
Posted Jul 10, 2020 - 19:53 UTC
Update
The start of this maintenance is confirmed to begin at 17:00 UTC on the 14th of July
Posted Jul 10, 2020 - 19:52 UTC
Scheduled
On the 14th of July 2020 beginning at 17:00 UTC, we will together with one of our third-party supplier carry out a scheduled maintenance on our platform. This maintenance will replace certificates on our external endpoints with certificates issued by DigiCert. We expect no impact to services as this change is by design seamless.
This can trigger an automatic certificate renewal for your DXP site(s) and to ensure seamless renewal, make sure that:

• Your application(s) support SNI certificates
• Your application(s) is NOT ‘pinned’ to the current certificate
• Your application allows DigiCert as root CA

If you have provided or purchased a dedicated certificate(s) for your website you are not affected by this maintenance.

If you have any questions, please contact support@episerver.com
Posted Jun 10, 2020 - 15:13 UTC